Mast Climbing Scaffold Inspection

 
 
 
 
Safety perimeter in place
 
Ground is stabile at base area
 
Base and mast are level and plumb
 
Overhead clear of obstructions to elevate platform
 
Bridges and extensions in good working condition
 
Tower structure, rungs in good condition
 
All bolts/pins installed
 
Platform deck in good condition
 
Step-down planks in good condition
 
All guardrails installed
 
No forward fall hazards presents (large openings on building)
 
Wall ties placed no more than every 20' vertically
 
Loads on platform distributed evenly
 
Fuel, engine and hydraulic oil at manufacturer's recommended levels
 
Hydraulic hoses in good condition
 
Electrical wiring in good condition
 
Battery and cables properly fixed
 
User guide on the platform
 
Operation of the platform/safety mechanism
 
Emergency switch buttons functional
 
All operators properly trained
 
Crane (if applicable)
 
All bolts and pins installed
 
Fuel, engine and hydraulic oil at manufacturer's recommended levels
 
Hydraulic hoses in good condition
 
Electrical wiring in good condition
 
Cable and hook in good condition
 
Cable stop properly installed to prevent over-lifting
 
Controlled access zone in place below lifting area
 
All operators properly trained